Policy
The WSIB issues a clearance certificate (clearance) to relieve a principal of liability for payment obligations to the WSIB that a contractor or sub-contractor may incur with respect to a contract entered into between the principal and the contractor or subcontractor during the validity period of the clearance.
NOTE
For information on obtaining clearances in construction, see 14-02-19, Clearance Certificate in Construction.
Purpose
This policy describes how a clearance protects the principal from a payment liability that the contractor or subcontractor may incur during the validity period of a certificate with the WSIB.
Guidelines
Definitions
Principal - A person or business entity awarding or letting a contract to a contractor or a subcontractor.
Contractor and sub-contractor - A person or business entity providing contractual services to a principal. The business relationship between a principal and a contractor includes the relationship between a contractor (the principal in this relationship) and a sub-contractor (the contractor in this relationship). Therefore, the term "contractor" includes sub-contractor in this policy.
General
This policy applies to all principals who let a contract to carry on a business activity in Schedule 1 or Schedule 2. It does not apply to householders who purchase services from a contractor.
A clearance also confirms that a contractor or subcontractor is registered with the WSIB and that its account(s) is/are in good standing.
Accounts in good standing
A clearance is issued if the following requirements are met. If the contractor has more than one account, each account must meet these requirements before a clearance is issued for any of the accounts
Advance payment
Before a clearance is issued for a newly registered contractor, or to a principal for a newly registered contractor, the contractor must make an advance payment for the amount determined by the WSIB.
Principal’s liability
By issuing a clearance, the WSIB waives its right to hold a principal liable for unpaid premiums and other amounts the contractor owes the WSIB, for the validity period of the certificate.
Limits to liability
If the contractor has payment obligations owing to the WSIB, the principal may be liable for the unpaid premiums and other outstanding amounts, up to the value of the labour portion of the contract(s) between the contractor and the principal.
Contractor’s obligations
A contractor must meet its registration, reporting and payment obligations to have its account in good standing.
Validity period
A clearance is valid for up to 90 calendar days, depending on the date that it is issued, and is renewable.
Exceptions
Contractor’s account not in good standing
When a contractor’s account is not in good standing a clearance may be issued if
Contractor’s account closed
Even though a contractor’s account is closed the contractor or the principal may request a clearance throughout the time period of the contract. In these cases the WSIB may issue a letter relieving the principal of liability if
If a clearance is issued for an overdue account, or a letter waiving liability is issued for a closed account, the validity period is determined by the WSIB taking into account the circumstances of the case.
Letter of credit
A contractor is permitted to post a letter of credit representing a disputed amount being appealed. A clearance is issued when the contractor has complied with all the requirements listed in “Accounts in good standing” and the letter of credit for the disputed amount is posted to the account. For more information, see 14-04-05, Alternative Payment Arrangements.
Retaining a clearance
Principals and contractors must keep record of clearances for at least three years from the date they were obtained.
Application date
This policy applies to all clearance decisions made on or after January 1, 2013.
Document History
This document replaces 14-02-04 dated January 2, 2014.
This document was previously published as:
14-02-04 dated January 2, 2013
14-02-04 dated June 15, 2012
14-02-04 dated April 7, 2008
14-02-04 dated October 12, 2004
14-02-04 dated September 28, 2001
08-03-06 dated July 25, 1996.
References
Legislative Authority
Workplace Safety and Insurance Act, 1997, as amended.
Section 141
Minute
Administrative